Default fee $300. New Jersey's PAVE pre-application process (a standard pre-application report with a fixed fee) may not be live at every utility yet. Where it is not, the utility's interconnection contact handles the request under its own procedure; the fee and content may differ. Fill the bracketed fields before sending.

Send it through the utility's interconnection page: https://nj.pseg.com/saveenergyandmoney/solarandrenewableenergy/solarpowersustanibility

Request letter

To: PSE&G, Interconnection (via https://nj.pseg.com/saveenergyandmoney/solarandrenewableenergy/solarpowersustanibility)
From: [your name]
Date: 2026-10-28

Subject: Pre-application report request, 5 MW / 20 MWh battery energy storage, [site address]

Dear Interconnection team,

[your name] requests a pre-application report for a proposed battery energy storage system at
[site address], in the PSE&G service territory.

Project: 5 MW / 20 MWh battery energy storage (charging and discharging),
planned connection at [planned connection voltage, kV] (PJM cycle route (69 kV and above)), front-of-meter.

We ask for the information a pre-application report usually carries for the nearest circuit and
substation: circuit name and voltage, substation name and transformer rating, peak and minimum
load on the circuit, existing and queued generation and storage, available hosting capacity for
injection and for withdrawal, known constraints (protection, voltage regulation, anti-islanding),
and any planned upgrades or cost-sharing projects affecting the circuit.

We understand the fee is $300 and will pay it on your invoice or through your
portal; please tell us if your current fee or process differs. A signed authorization from the
site owner or developer is attached.

Contact: [your name], [email], [phone].

Thank you,
[your name]

Authorization letter (for the site owner or developer to sign)

AUTHORIZATION FOR A PRE-APPLICATION REPORT

Date: 2026-10-28
Utility: PSE&G
Site: [site address and lot/block or parcel number]

I, [owner or authorized developer name], [title], of [owner or developer entity], confirm that
[entity] is the owner of the site above or holds a signed option or lease to develop it, and
authorize [your name] to request and receive a pre-application
report from PSE&G for a proposed battery energy storage system of about 5 MW at
this site, and to discuss the report's content with the utility on our behalf.

This authorization covers the pre-application report only. It is not an interconnection application
and creates no queue position.

Signed: ______________________________    Date: ______________
Name and title: ______________________________
Entity: ______________________________
Contact: [email], [phone]

GridArb drafts the request; the utility's own form or portal prevails where it has one. How we calculate.